Best Practices for Segmental Retaining Walls Best Practices

Disclaimer


The intent of this material is to communicate the best practices for design of Segmental Retaining Walls (SRW) as determined by Allan Block Corporation based on 25 plus years of research, design and field experience. This is not meant to be a final authority as each project has its own set of unique situations.

The local engineer of record must use their best engineering judgment to account for those situations that present themselves and provide a safe and efficient design for the customer. At no time does the contractor or local building official have the authority to override the approved plans and specifications provided from the local engineer of record.

It is the recommendation of Allan Block Corporation that the local engineer of record work for and be paid by the project owner. It has been determined that the local engineer of record should be the Project Site Civil Engineer as they are best suited to take responsibility for the design, and how it affects the site, whether they do the design in-house or use an outside consultant to do the design for the project.

The Project Site Civil Engineer has control of several of the overall aspects of the project and therefore is most able to properly handle the integration and communication required to ensure the performance of the wall complies with the needs of the site. For wall design applications that are outside of the experience level of the Project Site Civil Engineer, a wall designer with the appropriate knowledge and experience should be contracted with by the Project Site Civil Engineer. It is recommended that the wall contractor not be responsible for securing the engineering.

last updated: 1/14/2022

Chapter 8: Tall Wall Considerations

tall wall consideration

Pdf    dwg

Click on the topics below to view more information on the best practices for Allan Block segmental retaining wall design for residental and commercial applications.

Design Guidelines Item: The term, "owner" refers to the property owner or their designated representative.

8.1   Tall Wall Definition

8.1   Tall Wall Considerations are to be employed with structures rising to a height of between 3 – 4.6 m, depending on the application and thediscretion of the wall design engineer.

A 3 m high wall structure with a slope or structure above would be considered as a tall wall, while the same wall height constructed with a level condition above the wall without any additional surcharge may not require consideration as a tall wall.

Variable Wall Rock Thickness

Figure 8-1: Variable Wall Rock Thickness

Several factors may change a typical design when structures reach these defined higher levels such as the depth of wall rock, increased design parameters, enhanced structural fill and global stability analysis requirements.

8.2   Variable Rock Thickness at Face

8.2   Wall rock depth behind the block and material used.

  1. Site conditions and wall height should make the engineer consider expanding the depth and or size of material used.
  2. Typical wall rock depth will vary with wall height, if select/structural fill is not utilized in the reinforced mass, Figure 8-1.
    1. For wall applications between up to 3 – 4.6 m as discussed in section 8.1, 30 cm typical depth top to bottom.
    2. For walls from 3-6.1 m tall, the bottom half is suggested to be increased to 60 cm deep and the top half to be the typical depth of 30 cm deep.
    3. For walls over 6.1 m tall, the bottom half is suggested to be increased to 90 cm deep and the top half is divided in two with a 60 cm deep column and a 30 cm deep column at the top.

8.3   Compaction and Soil Considerations

8.3   For tall walls the engineer should increase design parameters of compaction and wall rock usage.

  1. Select/structural fill should be specified for the minimum bottom 1/3 to 1/2 of the reinforced fill. An Internal Compound Stability (ICS) analysis can aid the designer to determine if greater select/structural fill heights are required. The use of additional select/structural fill should extend to the entire length of the reinforcement. This fill material should have a PI of less than 6 for walls up to 6.1 m and for taller walls the material should have a PI of zero. An example of what type of fill should be considered for this area would be compactable sands or gravels.
  2. The engineer must carefully review the site geometry and structures above and below the wall to adequately plan for the use of the land placed into service by the retaining wall structure.
  3. Provide detailed requirements for onsite inspection to ensure that detailed specifications are complied with during construction. This includes, but is not limited to:
    1. Confirmation of the foundation soils
    2. Confirmation of the retained soils
    3. Verify the imported materials
    4. Confirm reinforcement material
    5. Verify the block
    6. Validate soil placement and compaction
      1. A single test/confirmation for each of the items listed would not be considered adequate. A detailed construction log should be used with sign offs at incremental levels by the responsible parties.
  4. Consider how much potential settlement will impact structures above the reinforced soil mass. Consider increasing compaction requirements from 95% of standard proctor to 98% to minimize settlement where essential to the application.
  5. A detailed review and implementation of a water management plan is essential. This should include a detailed drawing for water collection and water flow diagrams for both above and below grade drainage. Below grade utilities and above grade structures should be included in the overall site design to ensure that site details such as storm drains and curb and gutters do not influence the overall wall envelope or effect performance. Unless designed to accommodate hydrostatic loading, it is essential that the reinforced soil mass not be exposed to outside water sources that would rise above the level of incidental water.
  6. As walls get taller the internal stresses increase and depending on the soils used, can cause lateral loads pushing on the back of the facing. To minimize internal lateral loads on the Allan Block facing, it is recommended to utilize the described soils above and to expand the depth of the wall rock column behind the facing, See Section 8.2.b for more information. Expanding the wall rock zone behind the wall also reduces down drag forces on the geogrid caused by localized settlement and allows for easier compaction directly behind the block.
  7. In addition to the compaction and wall rock parameters, tall walls require the design engineer to evaluate the overall stability of the soil structure and the subsoils beneath the wall. The reinforced soil structure should be evaluated for internal settlement which may require additional select fill to mitigate. The subsoils cannot be ignored due to similar reasons. The overburden of the tall wall can cause unwanted settlements in the foundation material. Removal of the subsoils and replacement with quality select fill may be required to mitigate these possible settlements.

8.4   Increased Forces in Lower Portion of Walls

8.4   As walls increase in height the active earth forces also increase in the lower portion of the wall. Therefore it is not uncommon in taller walls to increase the strength of the lower geogrid layers or decrease the grid spacing to accommodate the higher design forces.

8.5   Global Stability of Tall Walls

8.5  The overall global stability of tall walls must be considered separately from the standard wall design to ensure the stability of the entire project site. For more information on global stability see Chapter 9.0 Global Stability - General and Chapter 10.0 Global Stability - Terraced.

8.6   Internal Compound Stability Calculations

8.6   Internal Compound Stability (ICS) calculations provide insight into potential global or overall stability issues. When more than 50% of the slip arcs originate at the back of the design envelope, as defined in Chapter 1, Section 1.7 b, a full global/overall stability analysis should be recommended to the owner by the owner’s geotechnical engineer.